The painting and rehab project begins on May 1st, and will be completed in November of 2011. This project includes a number of cosmetic repairs and modifications to the buildings plus new paint will be applied. This project will cost approximately $400,000 (about $1,000 per unit).
The map below shows the order in which buildings will be completed in which order. We will be doing this at the rate of about eight buildings per month, and an exact schedule will be published as work progresses. The buildings will be completed one at a time, beginning with powerwashing and repairs followed by painting, which will be done starting fairly early in the morning and working on the shaded side of the buildings to avoid painting on surfaces that are too hot, which will allow the paint to dry properly.